| Goal Programming Model For Production Planning In A Toothpaste Factory |
|
Goal Programming Model For Production Planning In A Toothpaste Factory
A.D. Adeyeye1 and O.E. Charles-Owaba2 1,2Department of Industrial and Production Engineering University of Ibadan, Ibadan, Nigeria 1 Địa chỉ email này đã được bảo vệ từ spam bots, bạn cần kích hoạt Javascript để xem nó. , 2 Địa chỉ email này đã được bảo vệ từ spam bots, bạn cần kích hoạt Javascript để xem nó. MRPII 17
ABSTRACT The GP model was developed for production planning in a toothpaste factory. Two objectives were distinguished: minimization of processing cost, and maximization of the capacity utilization of production facilities. Two priority structures were used to explore the trade-off options. When processing cost minimization was assigned the first priority, the utilizations of Processing Plant 1 and Filling Machine 2 were 20.32% and 0.18% respectively. When capacity utilization was assigned first priority, the processing cost increased by 7.55% but capacity utilization improved. The least utilized facility was Filling Machine 1 with a utilization of 43.85%. |