| Stability-Based Short-Term Capacity Requirement Planning under Uncertainty |
|
Stability-Based Short-Term Capacity Requirement Planning under Uncertainty
Haruhiko Suwaa, Daisuke Moritab
aSetsunan University, 17-8 Ikedanaka-machi, Newagawa, Osaka 5728508, Japan
bTakachiho University, 2-19-1 Omiya, Suginami-ku, Tokyo 1688508, Japan
∗Haruhiko Suwa. Tel/fax: +81-72-839-9309.
E-mail address:
Địa chỉ email này đã được bảo vệ từ spam bots, bạn cần kích hoạt Javascript để xem nó.
MRPII 45
Abstract
This paper proposes a newmethod of short-term capacity requirement planning (CRP) from the viewpoint of “stability”. The term stability refers to the higher predictability of a released capacity requirement plan (or a load plan), and also signi?es the robustness of a manufacturing process against internal/external uncertainties.
The objective of CRP mentioned in this study is to determine a stable allocation of each manufacturing resource to given operation orders with the aim of minimizing the probability that the resource requirement of each operation order exceeds the capacity of corresponding resource.
Through some computational simulations, it is demonstrated that the proposed CRP method is applicable as a short-term CRP method by applying it to a ?exible job-shop manufacturing system.
Keywords:
Capacity requirement planning; Schedule stability; Uncertainty; Resource-constrained project scheduling; Mathematical model |